
Rising to the Challenges of a Century of Deterioration
Cathedral Church of the Nativity Bethlehem, PA | Structural Reconstruction

Project Background
- Church's buildings were constructed in the late 19th century from quartzite stone
- 85-foot bell tower is one of Bethlehem's most prominent structures
- Decorative elements include traceries, battlement caps, parapet caps, buttress caps, belt courses, and water tables
- A century of natural weathering, combined with acid rain, freeze-thaw cycling, and improper repairs, had resulted in severe structural deterioration
Project Challenges
- Upper level of bell tower exhibited large vertical cracks
- Parapet walls were bulging and bowing
- Battlement caps and decorative parapet niche stones were deteriorated beyond reuse
- Limestone traceries showed severe cracking resulting from steel anchor corrosion and the stresses of adjacent displaced masonry
- Acrylic water repellent previously applied to church walls had been degraded by UV light and had turned white
- Naturally occurring iron deposits within the quartzite had rusted and bled down the church's walls
- Certain quartzite pieces had turned into a powdery, crumbling mass
- Many original mortar joints were cracked, eroded, or missing
- Blue sandstone was exhibiting extreme exfoliation, delamination, cracking, and loss of detail due to improper bedding plane orientation
- All work was performed very close to busy sidewalks and a major vehicular thoroughfare
Project Approach
- Three tons of new steel beams and channels were hoisted into the bell tower and welded, bolted, and grouted into place
- New lead-coated copper through-wall flashing was installed
- Replacement battlement caps were cast using a coloring agent that would match the appearance of the original bluestone
- Tracery limestone pieces were removed and reset
- A combination of high-pressure water blasting and abrasive grit blasting was used to remove water repellent stains
- Iron stains were removed with an ammonium bi-fluoride solution
- Crumbling quartzite pieces were removed and replaced
- All surface mortar was removed and painstakingly rebuilt with a historically accurate high-lime mortar
- Damaged blue sandstone sections were rebuilt using a proprietary stone patching material
- All scaffolding was wrapped with heavy-duty netting to prevent any accidents or injuries as a result of falling debris